Regular maintenance of mechanical equipment is essential. On the one hand, it is to improve the effect of the equipment, on the other hand, it is to prolong the service life. Next, xinchuangsh...
egular maintenance of mechanical equipment is essential. On the one hand, it is to improve the effect of the equipment, on the other hand, it is to prolong the service life. Next, xinchuangsheng machinery will share with you the lubrication and maintenance of the water mill wire drawing machine.
1. The water mill wire drawing machine shall be operated and maintained by a specially assigned person. The operator shall carefully read the operation manual before working and be familiar with the equipment performance and precautions.
2. Adjust the height of the worktable and the pressing rod according to the thickness and cutting amount of the workpiece to be processed.
3. Observe the working condition of the machine tool every time you start it. Pay attention to stop the vacuum work after the work stops.
4. In order to facilitate maintenance, adjustment and improve work efficiency, the wire drawing machine is equipped with manual and automatic working states.
5. Lubricate and maintain the wire drawing machine regularly according to the following requirements:
(1) After starting the machine each time:
a. When purging the machine tool with purified and filtered compressed air, pay attention to the cleanness of the inner surface of the conveyor belt and the upper surface of the workbench. There shall be no foreign matters on the surface of the sand pad and the sand belt, so as not to affect the sanding accuracy.
b. Regularly purge and wipe the sand belt swing control assembly, photocell and photoelectric switch to avoid insensitive sand belt swing.
c. When purging the water mill wire drawing machine, start the dust suction device.
d. Check the compressed air filter regularly and remove the condensate in the filter.
(2) After working for 40 hours, check the pressure sink air filter and fill it with sufficient lubricating oil.
(3) After 200 hours of work
a. Open the upper cover plate of the base of the wire drawing machine and apply grease on the worm gear to make it slide flexibly
b. Check the tension and wear of the narrow V-belt
c. Check the tension of the conveyor belt of the machine tool
d. Check the flatness of the workbench
e. Check the wear of pneumatic brake pads (replace if necessary)
(5) Lubrication and maintenance of reduction motor
a. Special lubricating oil shall be used for the reduction motor of the transmission belt (it has been filled when leaving the factory)
b. Oil change (filling) system:
Phase I: after 500 hours, the internal dirty oil shall be removed and replaced with new oil
Phase II: replace with new oil after 1000 hours
Phase III: replace with new oil after 2000 hours (replace every 2000 hours later)
c. Frequently check the oil level on the oil pressure gauge of the water mill wire drawing machine to keep the oil level at the center line of the oil gauge.